HomeCompleted ProjectsThe Vineyards I, II & III 350 Red Maple Rd, Richmond Hill, ON

The project scope consisted of replacing the central chilled water plant for 2 buildings as well as optimizing the operation of associated mechanical equipment for all fan coil systems. Hydro savings have been seen from both the peak demand kW reduction as well as he annual kWh decrease. Trinity Energy conducted the pre and post project measurement and verification. All values were checked and approved by the Local Utility Distributor during the Incentive application process.

 

Actual Reported kW Peak Demand Reduction 175.1 kW
Total Reported Annual kWh Savings 367,616 kWh
Total Incentives Accrued From OPA saveONenergy $118,092.81
Total Greenhouse Gas Emissions Reduction 247 Metric Tons per Year
(equivalent to 41 homes electricity usage)